White 2100x1000

Las Vegas Apartment Community Roof Coating

Multifamily Roof Coating • Las Vegas, Nevada • Elastomeric Restoration • Completed by Five Guys Roofing

Las Vegas Apartment Community Roof Coating: Restoring 17 Buildings Before Wear Turned Into Leaks

At Five Guys Roofing, we completed this roof coating project across a multifamily apartment community in Las Vegas. Some details have been generalized to protect resident and property privacy, while keeping the scope and process clear.

Before
Before photo of an aging foam roof in a Las Vegas apartment community with peeling coating and exposed patches
After
Aerial after photo of the recoated white roofs across the Las Vegas apartment community
Quoted Project Total
$94,545
Problem
Aging, worn foam roofing across 17 buildings, with peeling coating and exposed patches, prompting the property to plan a community-wide upgrade.
Solution
A full elastomeric recoat across all 17 buildings: cleaning, blister repair, and a two-coat reinforced coating system, plus a pipe jack replacement pass on the tile-roofed sections.
Result
A sealed, uniform white roof surface across the community with a 10-year workmanship warranty.

City

Las Vegas, NV

Property

Commercial multifamily community (17 buildings)

Roof Type

Flat / low-slope (foam roof)

Service

Full roof coating / restoration

Response Time

Scheduled visit

Time on Site

Multiple days (about 2 weeks)

Pricing and What Drives It

Quoted project total: $94,545. The primary cost drivers for this project were the scale of the community, at roughly 72,300 square feet across 17 buildings, and a pipe jack replacement pass on the tile-roofed sections.

Typical published range for this project type: $90,000+.

The Situation

The property reached out to Five Guys Roofing about the age of the roofing across the community and chose to move ahead with a planned, community-wide recoat rather than wait for problems to develop building by building.

What We Found:

  • The foam roofing across the community was showing its age
  • No emergency was reported — this was a planned, proactive project
  • The property wanted to extend the roofs’ life before issues developed

What Was Causing It

Inspection found aging, worn foam roofing with peeling coating and deteriorated patches across the buildings that needed to be addressed before recoating.

How We Verified the Roof Condition

Our team verified conditions with an on-site inspection ahead of scheduling the work, confirming the overall wear across the community and the areas that needed repair before coating.

  • Full walk of the roofs across the community to assess the foam roofing condition
  • Identified blistered and deteriorated areas needing repair
  • Checked penetrations, drains, and parapet walls for wear
  • Confirmed findings and scope with the property’s general contractor before finalizing the project

Supporting documentation included a signed proposal and a completion photo set.

The Plan

The scope for this job called for a full elastomeric recoat across all 17 buildings: pressure wash and clean the roofs, repair blistered areas, seal drains and cracked areas, then apply a two-coat elastomeric coating system, plus a separate pass replacing pipe jacks on the tile-roofed sections.

Materials and Components Used

  • Coating: white elastomeric coating, applied as base and top coats
  • Blister repair: polyurethane foam and 3-course repair for blistered roof areas
  • Drain and crack detailing: tytec membrane and coating at drains, scuppers, and cracked areas
  • Tile-roof sections: new aluminum pipe jacks (111 replaced)

Step-by-Step Work

1

Pressure Wash and Repair

We pressure washed and cleaned the roofs across the community to remove dirt and debris buildup, then cut out and repaired blistered areas using polyurethane foam and a 3-course repair before any coating went down.

2

Seal and Coat

We sealed drains, scuppers, and cracked areas with a 3-course repair using tytec membrane and coating, then applied a two-coat white elastomeric system across the roofs — a base coat followed by a top coat, carried 12 inches up the parapet walls for added protection.

3

Detail Work and Final Inspection

We detailed the coating around all roof penetrations, rooftop equipment, and AC units, cleaned the downspouts, and separately replaced 111 pipe jacks on the tile-roofed sections with new aluminum jacks. The site was cleaned and a final walk with the property’s general contractor confirmed the work met our quality standards before close-out.

Results

After completion, the community had a fully restored roof surface across all 17 buildings: a clean, sealed elastomeric coating system designed to resist water intrusion and extend the roofs’ service life.

Protection
A sealed two-coat elastomeric system with reinforced drains and seams reduces water intrusion risk.
Repairs
Blistered and deteriorated areas were repaired before coating, rather than coated over.
Appearance
A uniform white coated surface across all 17 buildings.
Quality
Final inspection and cleanup before handoff, with all penetrations and equipment detailed.
Warranty coverage:

The property received a 10-year workmanship warranty from Five Guys Roofing, along with free yearly inspections.

Before and After

A quick side-by-side recap of the roof before the recoat and after restoration.

Before
Before photo of the aging foam roof in the Las Vegas apartment community
After
After photo of the completed roof coating across the Las Vegas apartment community

FAQ

Why recoat roofs that aren’t leaking yet?

This property reached out about the age of the roofing across the community and chose to move ahead with a planned recoat rather than wait for active problems to develop.

What caused this project to move forward?

Inspection found aging, worn foam roofing with peeling coating and deteriorated patches across the buildings that needed repair before recoating.

What materials were used?

The system used a white elastomeric base and top coat, polyurethane foam and 3-course repair for blistered areas, tytec membrane and coating at drains and cracks, and new aluminum pipe jacks on the tile-roofed sections.

What affects the cost of a multifamily roof coating project?

This project’s quoted total was $94,545. The primary drivers were the scale of the community, at roughly 72,300 square feet across 17 buildings, and a pipe jack replacement pass on the tile-roofed sections.

Have more questions? Check out our FAQ page.

Need a Commercial Roof Inspection in Las Vegas?

If your property’s roofing is aging or showing wear, request an inspection. We’ll walk you through what we find and recommend the most reliable path forward.

Schedule Your Inspection